• Construction site with a traffic tower crane and a cherry picker in an urban area. Tall buildings and a partly cloudy sky in the background. American flags in the foreground.

  • Construction crane lifting a large structure or container at a high-rise building site, cloudy sky in the background.

  • A long, narrow underground room with server racks lining both sides, filled with electrical cables, pipes, and equipment.

  • Workers in safety vests and helmets working on an industrial electrical or mechanical system with metal pipes and control panels.

  • Group of construction workers and engineers standing together on a city street, wearing safety vests and helmets, gathered near a large red crane labeled "LIEBHERR" with construction fencing and a sidewalk in the background.

CONFIDENTIAL DATA CENTER  

Location: Denver, CO

Client: Confidential

Role: General Contractor

Project Value: $15M

Size: 6MW

Located in Denver’s interconnection alley, this confidential data center facility required critical infrastructure upgrades to support growing demand and enhanced interconnection capabilities. Our team was selected as the general contractor to deliver the mechanical, electrical, and plumbing (MEP) system upgrade of their active data center without disruption.

Key Deliverables

  • CRAC and ACCU Installation
    Installed four new CRAC units and four ACCUs, including crane hoisting to upper levels, rooftop placement, rigging, and return air plenum installation.

  • Refrigerant Piping System
    Provided new refrigerant piping systems with roof penetrations, pressure testing, and full charging with R-410a refrigerant. All work met rigorous performance and insulation standards.

  • Air Distribution Enhancements
    Furnished and installed over 100 return grilles (RG-2 and RG-4 series), including relocation and matching to existing aesthetics.

  • Controls Engineering
    Delivered complete controls programming and network integration for the new systems, including optimized sequencing, commissioning, and owner training.

  • Commissioning Support
    Supplied air balancing services and 40 hours of technician support to ensure a smooth and efficient commissioning process.

Results

The upgraded infrastructure now supports enhanced cooling efficiency, improved airflow, and integrated control systems. This project strengthened their capacity to support high-performance computing and connectivity needs in a mission-critical environment.